Construction Update for the Future of Sherman Health

May 12, 2009

IMG_5884

Sherman Health’s new hospital continues to make progress.  Here are our most recent construction updates:

Patient Tower
1.      Punch list activities continue on L2
2.      Carpet is being installed for the first 6 floors
3.      Ceilings are going in on Level 2 & Level 3

Hospital Construction
1.      Terrazzo is going down in dining room
2.      Drywall is being put up in the atrium area

Exterior Construction
1.      Trees are being delivered and installed
2.      Finishing concrete work
3.      Exterior doors are being installed

For more information about the construction process on the new Sherman Hospital visit our website. Be sure to watch the live web cam!

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: